93 - GARAŻ I SCHODY W WOLNEJ CHWILI

ŚCIANY PRAWIE GOTOWE NA PRZYJAZD PANELI (PRZYJADĄ ZA TYDZIEŃ) WIĘC ABY NIE TRACIĆ CZASU, ZACZYNAMY ŚCIANAMI GARAŻU, GDZIE BĘDZIEMY MOGLI UTOPIĆ TYCH 200 WORKÓW CEMENTU PRZED ZIMĄ LUB MIEĆ GDZIE WYLAĆ NADMIAR BETONU Z BETONIARKI (TA BĘDZIE WYLEWAĆ ŚCIANY W DOMU)

NAJPIERW OBIJAMY MŁOTKIEM OSTRE KRAWĘDZIE...

 MALUJEMY NA CZARNO PENETRACJĄ I MOŻEMY LEPIĆ


 PIERWSZA WARSTWA PRAWIE GOTOWA


 NIEBIESKI GLASTEK IDZIE NA SPODNIĄ WARSTWĘ, CZERWONY ELASTEK BĘDZIE NA NIM. TO POWINNO ZAPEWNIĆ WODOODPORNOŚĆ ŚCIAN GARAŻU :)
 OSTATNI KAWAŁEK PIERWSZEJ WARSTWY I CAŁY DZIEŃ LEPIENIA ZA NAMI.
ŚCIANA OPOROWA WCHODZĄCA W STOK, WSZYSTKO ZA NIĄ BEDZIE WYSYPANE ZIEMIĄ.


 DETAL WEWNĘTRZNEGO ROGU.

POMIĘDZY ŁAZIENKĄ I POKOJEM GOŚCINNYM CZAS PRZYGOTOWAĆ PODKŁAD POD SCHODY - MALOWANIE PENETRACJĄ, LEPIENIE IZOLACJI.

 KOLEJNY DZIEŃ I KOLEJNA WARSTWA IZOLACJI.
JEST I ON! GLASTEK + ELASTEK JUŻ NA SWOIM MIEJSCU. TERAZ WYMIERZENIE MIEJSC NA ZBROJENIE PIONOWE I WYWIERCENIE DZIUR DO BETONU.
WIDOK OD ULICY














WIDOK OD STOKU...












WIDOK OD OGRÓDKA SĄSIADA.