WZDŁUŻ GARAŻU DORABIAMY RESZTĘ ODWODNIENIA.
ZA TYLNIĄ ŚCIANĄ GARAŻU CAŁE ODWODNIENIE JEST JUŻ GOTOWE, CZAS PRZYŁĄCZYĆ KOLEJNY ODCINEK.
NA ŻWIR POŁOŻONA JEST AGROWŁÓKNINA, POTEM IDZIE RURA A NA NIĄ ŻWIR. CAŁOŚĆ ZAMYKA SIĘ AGROWŁÓKNINĄ JAK W WIELKIM RĘKAWIE ABY ZIEMIA NIE MIAŁA JAK DOSTAĆ SIĘ DO RURY.
A TU JUŻ WSZYSTKIE WARSTWY GOTOWE. JAK POWSTANIE ŚCIANA W GARAŻU, BĘDZIE MOŻNA ZASYPAĆ AŻ PO DACH!
FRANCUSKIE OKNA, ZE WZGLĘDU NA SWOJĄ WIELKOŚĆ MAJĄ SPECJALNE NADPROŻA.
MICHAŁ WYTUNINGOWAŁ DWUTEOWNIKI I PRZYSPAWAŁ TAKIE KAWAŁKI ŻELAZA, ABY WYLANY BETON MIAŁ CZEGO SIĘ TRZYMAĆ.
MÓJ DZIELNY SPAWACZ :D
POTEM WYLANE DWUTEOWNIKI MICHAŁ POSTAWIŁ NA SŁUPY.
TAK WYGLĄDA KONIEC NADPROŻA - DWA DWUTEOWNIKI WYLANE BETONEM I POSTAWIONE OBOK SIEBIE,
POZOSTAŁO TYLKO JE ZESPAWAĆ Z GÓRY I MOŻEMY LAĆ NA NIE BETON.
DO 6 PAŹDZIERNIKA, KIEDY PRZYWIOZĄ PANELE SUFITOWE, DORABIAMY JAKIEŚ PIERDOLKI A CZASEM NAWET SIĘ OBIJAMY :D